Single start and All tart

Latest updated: Dec 15, 2023
Video recording version: 8.0.0.483, compatible with BTS 8.0 software.

Today,we will demonstrate the differences between Single start and All start, as well as how to perform All start.


  • Open the BTS software, right-click on the test channel. You will see the first option as "Single start", which allows you to start testing on a single channel. 

  • Click on "Set" at the top, then click on "System settings", followed by "Display settings". 

  • In the Right-click menu function, locate "All start" and check the box.

  • Save the changes and enter the password "neware". 

  • Go back to the channel interface and right-click on the test channel to find the "All start" option. All start is mainly used for large-scale testing in enterprise production.


That wraps up the entire demonstration. Thanks for watching.

This operation video tutorial is applicable to the following products:
● CT-4000 Battery Testing System Series (CT-4008Q-5V100mA, CT-4008Q-5V6A-S1, CT-4008Q-5V6A-164, CT-4008Q-5V12A-S1, CT-4008Q-5V12A-164, etc.)
● CE-6000 Battery Testing System Series (Cell, Module, Pack, etc.)
● CT/CTE-8000 Battery Testing System Series (CT-8002Q-5V100mA, CTE-8008-5V200A, etc.)
● All-in-One Battery Testing System Series (WHW-25L-S-16CH, WIHW-200-160CH-B, WHW-100L-2-160CH, WHW-500L-5V6A80CH-380V, WGDW-380L-2-40BFC-5V600A8CH, etc.)



· Related Article

· Battery Exhibitions

· Popular Product

· Solution Scenarios

NEWARE and Cookies
We use Cookie to personalize and improve your experience with our website. By continuing to browse the site you are agreeing to our use of cookies.